Posted on: 28/03/2018

On behalf of Low Carbon Contracts Company (LCCC), we have issued a notice to Suppliers to inform them that the Total Reserve Amount (TRA) and the Interim Levy Rate (ILR) for Quarterly Obligation Period 1 July 2018 to 30 September 2018 are as follows:

  • Total Reserve Amount is £31,981,875.00
  • Interim Levy Rate is £4.224/MWh

On 9 April 2018 at 12:00, LCCC Forecasting team will be hosting a webinar on the Supplier Obligation Levy Rate and Total Reserve Amount determined for the Quarterly Obligation Period 1 July 2018 to 30 September 2018. This will include the background and assumptions applied and provide a 15 month forecast. To register for this webinar please email LCCC.

EMRC153 provides further details and highlights the keys dates for the Quarterly Obligation Period 1 July 2018 to 30 September 2018.